Valley line LRT cable replacement complete, fall opening anticipated – Edmonton

[ad_1]

TransEd announced on Thursday that the replacement of the cables on Edmonton’s Valley Line LRT has been completed and the company anticipates an opening date in the fall.

The Valley Line LRT expansion cost $1.8 billion and was originally supposed to begin passenger services in December 2020.

The cables had to be replaced because some were affected by oxidization. They were replaced with higher-quality cables, said TransEd, the private industry consortium contracted to build and operate the transit line.

“We upgraded the cables over the last nine weeks in order to make sure that when the lines open to passengers, we don’t have ongoing problems or issues that just kind of plague the system for a while. It was a much better solution,” said Dallas Lindskoog, communications manager for TransEd.

“Take the time now to shut everything down, kind of hit the reset, put these new cables in. So that the long-term system reliability is there for Edmontonians.”

Story continues below advertisement

These replacements should improve reliability for the next 30 years, TransEd said.


Click to play video: 'Express ETS bus route launches in Terwillegar as Valley Line LRT delays continue'


Express ETS bus route launches in Terwillegar as Valley Line LRT delays continue


TransEd is working with a group of three independent certifiers who are witnessing tests and receiving reports of testing done on the line to determine if the line is ready to open to passenger service.

Over the next few weeks, trains will operate along the 13-kilometre line, mimicking passenger services.

The Valley Line LRT will not use warning bells or crossing gates and will behave differently at intersections. Edmontonians are being asked to be aware of their surroundings.

“We’d like to remind Edmontonians to be vigilant and carefully follow all traffic rules and signage around the new line,” said Lindskoog.

For more information on safety visit the TransEd website.

Story continues below advertisement


Click to play video: 'Valley Line LRT signalling cable replacements coming'


Valley Line LRT signalling cable replacements coming


The Valley Line was first announced to be ready for passengers in December of 2020 but got delayed until the end of 2021.

In October of 2021, the opening was delayed again to the first quarter of 2022 but in December 2021 it was announced the line would be delayed until the summer of 2022.

In August of 2022, TransEd found dozens of cracks in the concrete support pillars and delayed the line again.

In August 2022, city manager Andre Corbould said Trans Ed is responsible for any costs that occur because of delays as Edmontonians are protected under the terms of the public-private partnership (P3) agreement for the project.

The Valley Line LRT is now anticipated to open to passengers for the fall of 2023.

Story continues below advertisement

“We know Edmontonians are anxious for transit and the city to announce an opening date,” Lindskoog said. “We continue to work closely with the city (for) more information about the opening date, which we anticipate will be this fall.”


Click to play video: 'Valley Line LRT issues raise concerns over P3 projects'


Valley Line LRT issues raise concerns over P3 projects